B4 – The activities of action B4 continue

Action B4 continues: Development of the protocol for the reduction of energy consumption and greenhouse gas emissions. The biokinetic and hydrodynamic models have been implemented by UNIFI and UGENT respectively,

Share
Action B3 completed

LESSDRONE has been used for the first official off-gas testing of this project in the aeration tanks of Cuoiodepur Water Resource Recovery Facility (WRRF). The aim of the tests is to

Share
B3 – Sixth measurement campaign at Cuoiodepur WRRF completed

In June 2020, the sixth of the 6 measurement campaigns planned at the Cuoiodepur WRRF was completed. The campaign, which was intended to measure oxygen transfer and the production of

Share
B3 – Fifth measurement campaign at Cuoiodepur WRRF completed

In January 2020, the fifth of the 6 measurement campaigns planned at the Cuoiodepur WRRF was completed. The campaign, which was intended to measure oxygen transfer and the production of

Share
B3 – Forth measurement campaign at Cuoiodepur WRRF completed

In November 2019, the forth of the 6 measurement campaigns planned at the Cuoiodepur WRRF was completed. The campaign, which was intended to measure oxygen transfer and the production of

Share
B3 – Third measurement campaign at Cuoiodepur WRRF completed

In October 2019, the third of the 6 measurement campaigns planned at the Cuoiodepur WRRF was completed. The campaign, which was intended to measure oxygen transfer and the production of

Share
B3 – Second measurement campaign at Cuoiodepur WRRF completed

In June 2019, the second of the 6 measurement campaigns planned at the Cuoiodepur WRRF was completed. The campaign, which was intended to measure oxygen transfer and the production of

Share
B3 – First measurement campaign at Cuoiodepur WRRF completed

In May 2019, the first of the 6 measurement campaigns planned at the Cuoiodepur WRRF was completed. The campaign, which was intended to measure oxygen transfer and the production of

Share
Action B2 completed

The drone has been tested under different operating conditions. The first tests were carried out in the laboratory to verify the functionality of the instrumentation and sensors, while at the

Share
Action B1 completed

The design and assembly of the equipment making up the LESSDRONE were completed. The automatic positioning of the hull and the analysis instrumentation are connected through a specific software that

Share